Wednesday, March 6, 2013

Scrum Events Timeboxing


All the events in Scrum are timeboxed and here is the list of key events and their timeboxes -
  • Sprint (also called as iteration) - 2 weeks (or as planned - between 2-4 weeks)
  • Sprint Planning Meeting - 8 hours*
  • Sprint Review - 4 hours*
  • Sprint Retrospective - 3 hours*
  • Daily Scrum Meeting (also called as Daily Standup) - 15 minutes (fixed regarless of sprint time)
* - time box given here is for a four week (one month) sprint - to be adjusted depending upon the sprint duration.