Wednesday, March 6, 2013

Scrum Events Timeboxing


All the events in Scrum are timeboxed and here is the list of key events and their timeboxes -
  • Sprint (also called as iteration) - 2 weeks (or as planned - between 2-4 weeks)
  • Sprint Planning Meeting - 8 hours*
  • Sprint Review - 4 hours*
  • Sprint Retrospective - 3 hours*
  • Daily Scrum Meeting (also called as Daily Standup) - 15 minutes (fixed regarless of sprint time)
* - time box given here is for a four week (one month) sprint - to be adjusted depending upon the sprint duration.

Saturday, March 2, 2013

Sprint v/s Iteration

Lets understand the difference between Sprint and Iteration in three easy steps -

1) Iteration is a generic Agile term that is used for any process thats iterative/repetative
2) An iteration in Agile Scrum is called a Sprint
3) Other Agile variants may or may not use same term to define iterative work, but these two are most common terms in use